Equipment preservation is the planned, recorded maintenance of equipment and materials from the moment they arrive on site until they are handed over to commissioning or operations, so that they are not damaged by corrosion, moisture, dust, vibration or lack of use. It covers storage conditions, protective measures such as covers, desiccants and nitrogen blankets, and periodic tasks such as rotating shafts and energising heaters, each carried out at a set frequency and recorded against the equipment tag. Done properly, it protects warranties and prevents expensive failures at start-up.

Preservation is rarely anyone's favourite job. It is repetitive, it happens in warehouses and laydown yards far from the critical path, and when it is done well nothing visible happens. When it is neglected, the consequences show up months later as seized bearings, flooded junction boxes and warranty claims that the vendor declines.

Why equipment preservation matters

Equipment on a major project can sit on site for a long time between delivery and commissioning. During that period it is exposed to conditions its designers did not intend: rain, humidity and condensation, dust, salt air, temperature swings and construction activity around it.

Typical failures from poor preservation include:

  • Brinelling and bearing damage on rotating equipment left stationary, especially where there is vibration from nearby work
  • Corrosion of machined surfaces, flange faces, shafts and internals
  • Moisture ingress into motors, switchgear and instrument enclosures, degrading insulation resistance
  • Seal and gasket degradation from drying out or UV exposure
  • Contamination of lube oil systems, internals and open piping with dust, debris and water

Warranties are the other reason. Most vendors attach storage and preservation requirements to their equipment and may refuse a warranty claim if the purchaser cannot show those requirements were met. The preservation record is your evidence.

Preservation during construction: the phases

Preservation responsibility and methods change as equipment moves through the project.

  1. Vendor shop and shipping. The vendor applies initial preservation for transport, usually documented in the vendor's preservation and storage instructions.
  2. Receipt and storage. On arrival, the receiving team inspects the equipment and its preservation, records its condition, and places it in the storage category the vendor specifies: indoor climate-controlled, indoor, covered outdoor or open yard.
  3. Installed, pre-mechanical completion. Once set in position, equipment is still exposed to construction. Preservation continues, often by the installation contractor, and may need to change: covers get disturbed, heaters need temporary power.
  4. Mechanical completion to commissioning. As systems are handed to commissioning, preservation responsibility typically transfers with them. Some preservation is removed as part of pre-commissioning; some continues until the equipment is in service.
  5. Handover. Any equipment not yet in regular operation needs its preservation status clearly handed over to operations.

Responsibility at each transfer should be written down. The gap between "construction has handed it over" and "commissioning has picked it up" is where preservation tasks most often lapse. For how these transfers are certified, see mechanical completion explained.

Typical preservation tasks by equipment type

Always follow the vendor's instructions first; where they are missing, the project preservation procedure fills the gap. The table below shows the kind of tasks commonly specified. Frequencies are indicative and should be set by the vendor or the project procedure.

Equipment typeTypical preservation tasksTypical frequency
Pumps, compressors, fansRotate shafts by hand a set number of turns to a different rest position; check covers and desiccant; check oil level or oil mist; confirm flanges blankedWeekly to monthly
Electric motorsEnergise anti-condensation heaters; rotate shaft; periodic insulation resistance check; keep terminal boxes sealedHeaters continuous; checks weekly to monthly
Switchgear, MCCs, panelsEnergise panel heaters or maintain climate control; check seals and door gaskets; keep cable entries sealedWeekly to monthly
TransformersCheck oil level, gas or nitrogen pressure and breather desiccant conditionMonthly
Vessels, exchangers, columnsMaintain nitrogen blanket and record pressure, or check desiccant and VCI; confirm nozzle covers intactWeekly to monthly
ValvesStore in the position specified by the manufacturer; end caps on; stroke actuated valves where specifiedMonthly or as specified
Instruments and analysersStore indoors in controlled conditions until installation; once installed, keep covers on and entries sealedMonthly inspection
Piping spools and flangesFlange face protection, end caps, drainage of any retained water after testingInspection monthly
Cable drumsSeal cable ends; store drums correctly on bearers; check for damageMonthly
Batteries and UPSCharge maintenance per vendor; check electrolyte or voltagePer vendor

Some tasks depend on conditions rather than the calendar. After heavy rain, a check of covers and enclosures is worth more than the scheduled monthly round. Coastal and humid sites generally need more frequent checks than dry inland sites.

Building a preservation checklist

A preservation checklist should be specific to the equipment type and, where the vendor has special requirements, to the individual tag. At minimum it records:

  • Tag number and description
  • Storage location and storage category
  • Vendor preservation instruction reference
  • Each required task, with its acceptance criterion (for example "nitrogen pressure within the range stated on the vendor data sheet", "shaft rotated and rest position changed")
  • Result: done, not done, or defect found
  • Any defect raised, with a photo
  • Name, date and signature of the person carrying it out
  • Next due date

Generic "equipment inspected: OK" checklists are close to worthless as evidence. If a vendor later asks whether the heaters were energised continuously, a tick in a box marked "OK" will not answer the question.

Preservation records: what good looks like

Preservation records are part of the equipment's history and, on most projects, part of the handover dossier. Good records:

  • Are linked to the tag. Preservation history should be retrievable for any tag in the tag register, not buried in a weekly spreadsheet per warehouse.
  • Show every due task and its status. Missed tasks are visible as missed, not silently absent.
  • Capture defects and actions. A failed nitrogen pressure check leads to an action and a follow-up record.
  • Are auditable. Who did what, when, with photos where it matters.
  • Survive transfers. When responsibility moves from the warehouse to construction to commissioning, the history moves with the tag.

Auditing preservation is straightforward once records are structured this way: pick a sample of tags, compare the tasks due against the tasks recorded, and physically check a few of them. Overdue tasks by equipment type and by responsible party is the one report worth reviewing every week.

Long-term storage of equipment

When equipment will be stored for an extended period, for example because of a delayed construction sequence or early procurement of long-lead items, the vendor may specify long-term storage measures beyond normal preservation. These can include full internal preservation with oil or VCI, filling with nitrogen, removal and separate storage of sensitive components, or climate-controlled storage.

If storage is going to exceed the period the vendor's instructions assume, contact the vendor early. Some requirements can only be applied before the equipment is packed away, and some warranties specify inspection by the vendor before start-up after long storage.

Removing preservation before commissioning

Preservation that protects equipment in storage can damage it in service. Preservation removal should be planned and recorded as carefully as preservation itself.

Typical removal activities include:

  • Removing desiccant bags, VCI emitters and temporary covers from inside equipment and enclosures
  • Flushing or draining preservation oils where the vendor requires it, and filling with the correct operating lubricant
  • Venting nitrogen blankets safely, with the confined space and asphyxiation risks managed
  • Removing flange covers, blanks and temporary plugs, and confirming each is logged as removed
  • Switching off temporary heater supplies and restoring permanent circuits

Removal is usually built into the pre-commissioning ITRs or checklists for the equipment, so it is signed off before the equipment is run. A forgotten desiccant bag inside a compressor or a blind left in a line is a start-up failure waiting to happen. Many projects keep a register of temporary items for exactly this reason. For the stages that follow, see cold commissioning vs hot commissioning.

Common preservation failure modes

  • No owner at handover points. Tasks lapse between warehouse, construction and commissioning.
  • Heaters without power. Anti-condensation heaters are specified but the temporary supply is never installed or is disconnected by another trade.
  • Records by exception only. Only problems are recorded, so there is no evidence that routine tasks were done.
  • Generic frequencies. The vendor's specific requirements are ignored in favour of a blanket monthly check.
  • Preservation removed too early. Covers and blinds come off at installation, leaving equipment exposed for months before commissioning.

Managing preservation in Accord

Accord includes a forms engine for building, versioning and digitising preservation, construction and commissioning forms, with OCR for scanned paper records and form-to-PDF output. Forms sit against the equipment and items catalogue and the Project → System → Sub-system → Equipment/Tag hierarchy, so preservation history stays with the tag as responsibility moves through the project. Works planning, scheduling and task boards help plan recurring preservation rounds, dashboards report completion, and handover dossiers can draw on the same records.

Frequently asked questions

Who is responsible for equipment preservation on a construction project?

It depends on the contract and the phase. Commonly the vendor is responsible until delivery, the contractor's materials or warehouse team while equipment is stored, the installation contractor once it is installed, and commissioning or operations after the system is handed over. The preservation procedure should state each transfer point.

How often should preservation checks be carried out?

Follow the vendor's instructions. Where those are silent, the project preservation procedure sets frequencies, commonly weekly to monthly depending on the equipment and site conditions. Some measures, such as motor and panel heaters, are continuous and only their status is checked periodically.

What happens to the warranty if preservation is not carried out?

That depends on the purchase order and vendor terms, but many vendors make warranty conditional on storage and preservation in line with their instructions. Without records showing that preservation was done, a warranty claim may be disputed. Check the specific purchase order conditions.

Are preservation records part of the handover dossier?

On most industrial projects, yes. Owners typically want the preservation history for each item, especially for rotating equipment and electrical equipment, so they can judge its condition and support any warranty claims. Check the owner's handover requirements for the exact scope.

Does preservation stop at mechanical completion?

No. Preservation continues until the equipment is in regular service, which may be long after mechanical completion. What usually changes at MC is who is responsible and, for some items, the method, as some preservation is removed as part of pre-commissioning.