A non-conformance report (NCR) in construction is a formal record that work, materials or a process do not meet a specified requirement, whether that is a drawing, specification, code, procedure or approved ITP. It describes what is wrong, contains the affected work, records the decision on what to do about it (the disposition) and tracks the correction and any corrective action through to verified close-out. Unlike a punch item, an NCR usually needs an engineering or client decision, not just a fix.

When to raise an NCR vs a punch item

This is the question site teams get wrong most often, in both directions. Raise too many NCRs and the system clogs with trivia. Raise too few and genuine quality failures are hidden in a punch list where nobody analyses them.

A practical test is to ask whether the fix is obvious and within the design, or whether someone has to decide what "acceptable" now means.

SituationUsually a punch itemUsually an NCR
Missing label, loose gland, paint damageYes
Work incomplete but installed correctly so farYes
Weld rejected by NDT, repairable under the welding procedureOften, depending on project rulesSometimes, especially if repeated
Wrong material grade installedYes
Dimensions outside tolerance, fix needs engineering inputYes
Concrete test results below specified strengthYes
Hold point worked past without releaseYes
Uncalibrated instrument used for an acceptance testYes
Repeated defect of the same type across many tagsYes, for the systemic cause

Many projects write this into the quality plan, and some treat a failed ITR as an automatic NCR for specific activities. Terminology also varies; you will see "non-conformity", "NCN" and "quality deviation". Follow your contract's definitions. For how punch items are categorised, see punch list categories A, B and C.

NCRs against processes, not just products

An NCR doesn't have to be about physical work. Working past a hold point, using an unqualified welder, or inspecting with an out-of-date drawing are all non-conformances, even if the finished work turns out to be fine. These process NCRs are often more valuable than product ones, because they reveal the reason defects happen. See hold points and witness points for why missed holds are treated seriously.

What an NCR must contain

An NCR that says "pipe support wrong, please fix" will be argued about for weeks. A good one can be understood by someone who wasn't there. Include:

  1. Unique NCR number, date and originator.
  2. Location and identification: tag numbers, system, drawing and revision, area, or batch or heat number for materials.
  3. The requirement: exactly which document and clause, or which ITP line, was not met.
  4. The non-conformance: what was found, stated as fact, with measured values where relevant.
  5. Evidence: photos, test results, marked-up drawings.
  6. Containment: what has been done immediately, such as quarantine tags, stopping further work, or checking other items from the same batch.
  7. Responsible party: the contractor or supplier who must respond.
  8. Proposed disposition and technical justification.
  9. Approvals: who accepted the disposition, including the client or designer where required.
  10. Correction verification: how and by whom the fix was checked, with the re-inspection record.
  11. Root cause and corrective action, where required.
  12. Close-out signature and date.

NCR example (wording)

Requirement: Specification section for structural steel, and drawing S-2104 rev C, require M20 grade 8.8 bolts at baseplate connections on pipe rack PR-03. Non-conformance: Six baseplate connections on grid lines 4 to 6 are fitted with M20 grade 4.6 bolts, identified by head markings. Photos attached. Containment: Area barriered; no further loading of PR-03 pending disposition. Remaining pipe rack connections to be checked against the bolt register.

Notice what it doesn't do: blame anyone, speculate on cause or propose the fix in the description. Those come later.

NCR disposition options

The disposition is the decision on what to do with the non-conforming item. The usual options are:

DispositionMeaningTypical approval
Use as isAccept the item without change, with technical justificationDesigner or engineer of record; usually client
RepairMake it acceptable for use, though it may still differ from the original requirementEngineering, and often client
ReworkBring it fully into line with the original requirementContractor QC, with re-inspection
Reject / scrapRemove and replaceContractor QC
Return to supplierFor non-conforming materials or equipmentContractor procurement and QC

"Use as is" and "repair" change what is being handed over, so they typically need approval from whoever holds design authority, and they should be reflected in as-built records. Many contracts call an accepted departure a concession. Treat these as formal decisions with a signed justification, never as a verbal agreement on site.

The NCR process step by step

  1. Identify and record. Anyone can raise a potential non-conformance; QC confirms it and issues the NCR.
  2. Contain. Stop the problem spreading: quarantine, tag, stop work on the affected item, check related items.
  3. Notify. Inform the responsible party and, where the contract requires it, the client within the stated period.
  4. Propose disposition. The responsible party proposes a disposition with technical justification.
  5. Approve disposition. The appropriate authority accepts, rejects or amends it.
  6. Correct. Carry out the approved repair, rework or replacement.
  7. Verify. Re-inspect or retest, record the result on a fresh or updated ITR.
  8. Investigate root cause where the NCR is significant or part of a trend.
  9. Take corrective action to prevent recurrence.
  10. Close. QC and, where required, the client sign it off.

Correction (fixing this item) and corrective action (stopping it happening again) are different things. Many NCRs are closed after correction alone, which is why the same defects keep appearing.

Root cause and corrective action in construction

For isolated, low-impact NCRs, a short cause statement is enough. For significant or repeated ones, use a structured method: "five whys" is usually sufficient on site, and a fishbone diagram helps when several factors are involved.

Look past the individual. "Fitter used wrong bolts" is not a root cause. Ask why the wrong bolts were available at the workface, why the bolt grade wasn't on the work pack, and why the inspection didn't catch it sooner. Typical real causes are unclear drawings, mixed stock in laydown, inadequate briefings and inspection happening too late.

Corrective actions should be specific, owned and dated, such as segregating bolt grades in stores, adding grade to the ITR as a check item, and briefing the crews, and then checked for effectiveness a few weeks later.

How NCRs affect completion and handover

An open NCR on a tag is a real risk to completion. Depending on project rules, it may block the ITR from being accepted, prevent a system reaching mechanical completion, or be carried as a punch item with an agreed category. Accepted concessions need to be in the handover records so the operator knows what they are receiving. Link each NCR to the tags and systems it affects, so its status appears where the certificate decisions are made. How the certificates depend on each other is covered in commissioning certificates explained, and the quality plan's role in setting the NCR process is covered in how to write a construction quality plan.

Common NCR mistakes

  • Using NCRs as a weapon between contractors, so people avoid raising them.
  • Vague descriptions without the requirement reference.
  • No containment, so the same problem is repeated on the next twenty items.
  • "Use as is" without a technical justification or the right approval.
  • Closing on correction alone, with no look at root cause for repeats.
  • NCR logs kept separately from the completions system, so open NCRs surprise everyone at certificate time.

Managing NCRs in Accord

Accord manages NCRs alongside punch items, safety observations and site or technical queries in one integrated issue register, with Category A/B/C criticality and stage-gate blocking so open issues are visible where certificates are decided. Issues sit against the system and tag hierarchy, supporting documents are held in a revision-controlled library, and changes arising from an NCR can go through change requests with impact assessment and approval workflows. Every action is recorded in an immutable audit log.

Frequently asked questions

What is an NCR in construction?

An NCR is a non-conformance report: a formal record that work, materials or a process do not meet a specified requirement. It documents the problem, containment, the agreed disposition and verification of the fix. Significant NCRs also record root cause and corrective action.

How do you write an NCR?

State the requirement that was not met, with the document reference, then describe what was found in factual terms with evidence such as photos and measurements. Identify the affected items precisely, record any containment, and leave the disposition and root cause to the later stages of the process. Write it so someone who wasn't on site can understand it.

What is the difference between an NCR and a punch item?

A punch item is usually an incomplete or defective detail with an obvious fix within the design. An NCR is raised when a specified requirement hasn't been met and a decision is needed on whether and how the item can be accepted. Your quality plan should set the dividing line for your project.

What are the NCR disposition options?

The common dispositions are use as is, repair, rework, and reject or scrap, with return to supplier for materials. Use as is and repair usually need approval from the design authority and often the client, because they change what is handed over.

Who closes an NCR?

Normally the contractor's QC function closes the NCR once the correction has been verified, and the client signs off where the contract requires it. Closure should reference the re-inspection or retest record, and for significant NCRs the corrective action should also be complete or tracked separately.